Located in Zhijin County, Guizhou Province, it is the auxiliary purely low-temperature WHR EPC general contracting project of one 2,500t/d cement clinker production line. Configured with two boilers and one power unit in its layout design, it has an installed power of 5MW and a total construction period of nine months. The actual start-up date of the project was May, 10, 2013, and it was combined to grid on February, 10, 2014. Currently preparations are being made on site for performance assessm