Guizhou Nayong Longqing Wujiang Cement 2500t/d Cement Clinker Production Line WHR Project

Date:2013-07-31

Guizhou Nayong Longqing Wujiang Cement 2500t/d Cement Clinker Production Line WHR Project

This is a 2500t/d cement clinker line equipped with WHR unit in EPC construction mode. It’s equipped with 2 boilers and 1 turbine. Turbine& generator’s power capacity is 5MW. The construction period is 9 months. The project is started on 5th August, 2013 and realized with electricity generating on 21st, April. On 24th July, the project passes the performance test.