This is a 2500t/d clinker production line equipped with WHR unit in EPC construction mode. The unit is designed with 2 boilers and 1 turbine. Turbine and generator’s installed power capacity is 4.5MW. The total construction period is 11 months. The project is actually started on 8th September, 2012, and realized with electricity generating on 22nd October. The project passes the performance test on 22nd November, 2013.